Client: |
|
Thiess John Holland Joint Venture |
Main Contractor: |
|
Thiess John Holland Joint Venture |
Foundation Contractor: |
|
Piling Contractors Bauer Australia Joint Venture |
Scope of work: |
|
Construction of secant piles (880mm and 1180mm diameters) and bored |
Construction Period: |
|
May 2009 – June 2010 |
Construction work on the $4.8bn Airport Link project in Brisbane commenced in December 2007. This major piece of infrastructure involved the construction of a 6.7km long road to Brisbane airport, extension of the existing Northern Busway to Kedron and the upgrading of the existing Airport Roundabout. The 11kms of tunnels require the use of two Tunnel Boring Machines (TBM). All three sections of work were completed by the middle of 2012.
To form the complex intersections along the route, secant pile walls were installed so that cut-and-cover tunnels could be excavated. Bauer also constructed foundation piles for a large number of bridges at the intersections.
Six Bauer BG piling rigs were used to install the piles over the period from May 2009 to June 2010.
BAUER Foundations Australia Pty. Ltd.
Ground Floor
154 Enoggera Road
Newmarket 4051
Brisbane
Australia
Phone: +61 7 3352 7444
Fax: +61 7 3352 7244
e-mail: info@baueraustralia.com.au
Copyright © , All Rights Reserved